We are travelling to Spain for a maintenance visit on the 15th October for around 10 days, so piers will be up and down a little over this time as we get through the list of work.

The main work being carried out:

  • Pier-1 collimation tweak, new calibration frames in preparation for 1x1 binning
  • Pier-2 new 10 micron Gm2000 mount plus general maintenance, new calibration frames in preparation for 1x1 binning
  • Pier-5 flight collimation tweak
  • Pier-6 flight collimation tweak
  • Pier-8 sort secondary spacing out & general maintenance
  • Pier-9 fit new focuser & camera
  • Pier-10 service the Paramount ME & tweak collimation
  • Pier-14 Sort out the ZWO obligatory tilt issue out once and for all
  • Fit a customers new Hosting setup
  • Prepare all piers for upcoming winter season
  • Fit new flat panels where possible

Steve & Pete


Please ignore my dylexia wherever possible, just be thankful I can control my Tourettes ;)

Things to do, so little time!

Steve
Roboscopes Tea Boy


There are no replies made for this post yet.
Be one of the first to reply to this post!

Follow Us

Newsletter

Proud to use

  • FLI

  • 656 Imaging

  • 10 Micron

  • Planewave

  • ZWO

Company Details:

Roboscopes

802 Kingsbury Road
Birmingham
B24 9PS
United Kingdom


Roboscopes is a trading name of ENS Optical LTD ¦ Copyright© 2020 Roboscopes
Cron Job Starts