We are in Spain doing maintenace at present, so some piers are down while we perform work. This cannot be helped
- P1 camera swapped - almost back up and running
- P2 camera swapped - awaiting new model then back up
- p3 doing new calibration filtes and flats for new 1x1 binning
- P5 part way through new wheel and full collimation
- P6 new camera - not started yet
- p8 new camera fitted and 30% finished
- P9 finished waiting new model and focus curves
- P10 new mount and full service - 50% complete
- P11 not started yet
- P12 not started yet - new camera
- p14 is back up and running
As per our normal practice we send what data has been completed or part completed so older subs dont get mixed up. All you need to do is resubmit once the pier is back up and you have the new camera angles from test jobs